Primary Building Update 4: 6th June, 2016

The primary school rebuild is progressing according to plan however we did experience a delay early on when it was discovered that the soapstone foundation near the green cottage was at a lower level than the engineering surveys had indicated.  This potential downside we have turned into a benefit as we’ll now create some extra space to be used for  storage and activity rooms.