Construction Updates - April, 2017

28.04.17

We have ongoing work at 4 places on site.

  1. 1.       Think tank
  • Installation of gutter
  • Installation of fascia board
  • Fitting in slab for plumbing installation in the floor
  1. 1.       J Block
  • Steel fixing for the beam
  1. 2.       L Block
  • Overhang roof installation
  1. 3.       Bridge
  • Pouring of concrete in the wings

These are some of the works being carried out at the moment.

27.04.17

These are the update of the ongoing work in school premises today:

  1. 1.       Think Tank
  • Installation of the alcopanel – fascia board
  • Plastering works on the column
  1. 2.       J Block
  • Steel fixing for the beam
  1. 3.       L Block
  • Installation of roof for the overhang in the basement
  • Clearing of soil and debris in the basement
  1. 4.       Bridge
  • Steel fixing works
  • Setting up the decking for pouring concrete

Most of the works was hindered today because of the rain. Some works will be carried out in the afternoon in L Block for the defects identified by AAPi Designs.

26.04.17

We have ongoing work at 4 places on site.

  1. 4.       Think Tank

There will 2 shifts today at Think Tank. First shift will be normal 7.30am to 5pm and the other one will be 2pm to 11pm. We opted for two shift so that the heavy machinery works can be carried out in the afternoon shift without disturbing the classes in L  block. The following are works that is being carried out today:

  • Roof framing
  • Plastering the column.
  • Fire and Electrical works are being carried out simultaneously
  • Framing for gutter
  • Filling concrete column – this will be carried out from 2pm to 11pm
  1. 5.       J Block
  • Steel fixing for the beam
  1. 6.       L Block
  • Overhang roof installation
  1. 7.       Bridge
  • Fitting of culvert
  • Mount headwall
  • Steel bending and fixing

These are some of the works being carried out at the moment.