Construction Updates - June, 2017

29.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

o   Fitting rug in the bottom of Think Tank

o   Plastering the basement

  • 2. Site B

o   Digging to make an emergency egress

o   Setting up area for new AstroTurf

3.       J-Block

o   Bending and cutting steel for work in the emergency egress

 

28.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

o   Fitting rug in the bottom of Think Tank

o   Plastering the basement

  • 2. Site B

o   Digging to make an emergency egress/fabrication of steps

o   Setting up area for new AstroTurf

3.       J-Block

o   Bending and cutting steel for work in the emergency egress

 

27.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

o   Fitting rug in the bottom of Think Tank

o   Plastering the basement

  • 2. Site B

o   Digging to make an emergency egress

o   Setting up area for new AstroTurf

3.    J-Block

o   Bending and cutting steel for work in the emergency egress

 

 

26.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

o   Fitting rug in the bottom of Think Tank

o   Plastering the basement

 

2. Site B

o   Digging to make an emergency egress

o   Setting up area for new AstroTurf

3.  J-Block

o   Bending and cutting steel for work in the emergency egress

 

23.06.2017

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

 

The Think Tank is open as emergency egress only some works are being carried out after school. Due to rain there was a lot of work disruptions

o   Cleaning around Think Tank

o   Touch up works

o   Leveling the floor in the basement

o   Fixing iron for basement floor

 

2. J Block (Site A)

o   Setting up scaffolding for pouring in column

o   Laying blocks

 

22.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

The Think Tank is open as emergency egress only some works are being carried out after school.

o   Cleaning around Think Tank

o   Touch up works

o   Fixing in chambers for electrical fitting and water outlets

o   Leveling the floor in the basement

2. J Block (Site A)

o   Laying blocks

o   Setting up scaffolding for pouring in column

3. Ground near maintenance

o   Clearing the stockpile

o   Fitting in culvert for driveway

 

 

21.06.2017

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

The Think Tank is open as emergency egress only some works are being carried out after school.

o   Cleaning around Think Tank

o   Touch up works

o   Fixing in chambers for electrical fitting and water outlets

o   Leveling the floor in the basement

2. J Block (Site A)

o   Laying blocks

o   Setting up scaffolding for pouring in column

 

3. Ground near maintenance

o   Clearing the stockpile

o   Fitting in culvert for driveway

 

 

20.06.2017

 

We have ongoing work at 3 places on site.                                 

  1. Think tank (Site C)

 

The Think Tank is open as emergency egress only some works are being carried out after school.

o   Cleaning around Think Tank

o   Installing pan and cistern in toilets

o   Touch up works

o   Fixing in chambers for electrical fitting and water outlets

o   Leveling the floor in the basement

2. J Block (Site A)

o   Laying blocks

o   Fitting in the column

3.       Ground near maintenance

o   Clearing the stockpile

o   Fitting in culvert for driveway

 

19.06.2017

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

The Think Tank is open as emergency egress only some works are being carried out after school.

 

o   Cleaning around Think Tank

o   Putting in tiles for the toilets

o   Touch up works

 

2. J Block (Site A)

o   Laying blocks

 

16.06.2017

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Correcting any defects

o   Fitting in vinyl and aluminum doors for the toilets

o   Installing night lights (sunset switched)

 

2. J Block (Site A)

o   Aligning in the columns for pouring cement

 

15.06.2017

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   General clean-up

o   Correcting any defects

 

2. J Block (Site A)

o   Aligning in the columns for pouring cement

14.06.2017

 

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   General clean-up

o   Correcting any defects

2. J Block (Site A)

o   Putting in the column

13.06.2017

 

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Putting in tiles for the toilets

o   Correcting any defects

 

2. J Block (Site A)

o   Tying column rod

12.06.2017

 

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Putting in tiles for the toilets

 

2. J Block (Site A)

o   Tying column rod

o   Setting scaffolding for fitting in column

10.06.2017

 

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Painting the fence post

 

2. J Block (Site A)

o   Building ram to move culvert to level 1 floor

o   Fabricating steel for beam level 1

 

09.06.2017

 

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Fitting in V-drains

o   Painting the fence post

o   Putting in chain link for fence

 

2. J Block (Site A)

o   Steel fixing works

 

08.06.2017

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Fitting in V-drains

o   Putting in tiles for the toilets

o   Painting the fence post

o   Putting in chain link for fence

 

2. J Block (Site A)

o   Pouring cement for  Block J floor

 

07.06.2017

We have ongoing work at 2 places on site.                                 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Fitting in V-drains

o   Putting in tiles for the toilets

o   Running data cable

o   Fitting in retaining wall near sandpit

o   Painting the fence post

 

2. J Block (Site A)

o   Steel fixing works on the decking

Due to rain we had disruption to the works, in J Block works can only be done when the its not raining.

 

06.06.2017

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Fitting in the railings

o   Cleaning around Think Tank

o   Fitting in V-drains

o   Putting in tiles for the toilets

o   Running data cable

o   Fitting in retaining wall near sandpit

o   Painting the fence post

 

2. J Block (Site A)

o   Steel fixing works on the decking

o   Other preparation for pouring in cement


05.06.2017

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Clean-up around the think tank

o   Installing the lights and switch

o   Fitting in the railings

 

2. J Block (Site A)

o   Setting in final decking and rod for filling in floor

 

Most of the workers are working near the Think Tank doing cleaning and removing scaffolding.

 

02.06.2017

We have ongoing work at 2 places on site.                                 

 

  1. Think tank (Site C)

o   Finishing works – painting, plastering

o   Removal left over material and scaffoldings

o   Fitting in the railings

o   Cleaning around Think Tank

 

2. J Block (Site A)

o   Putting in fire and electrical conduit

o   Preparing the decking for pouring in cement - ongoing

                             

01.06.2017

 

We have ongoing work at 2 places on site.

1. Think tank (Site C)

 

o   Finishing works - painting, plastering

o   Installing the lights and switch

o   Fitting in the railings

o   Cleanup of Think tank area

 

2. J Block (Site A)

 

o   Fixing the decking for filling in the floor for Level 2